as a water cut-off for the project. HFDI completed the  
 sheet  pile  and  steelwork  installation  while  Southwest  
 Contracting, Ltd., installed the anchors. 
 The cost of the entire sewer and water project is estimated  
 at $1.3 billion. The project tab is being shared by all  
 Metro Vancouver member jurisdictions that are part of  
 the Greater Vancouver Sewerage and Drainage District.  
 The pump station and adjacent Sanitary Sewer Overflow  
 tank are projected to cost about $70 million at buildout. 
  Katzie First Nation artist, Trenton Pierre, who has  
 earned praise for local murals, has been awarded the contract  
 to create a full-wall design on the south wall of the  
 storage tank. 
 Community input for the project  was ongoing and  
 inclusive. Reports show that consultations took place in a  
 series of three open houses held between 2017 and 2019,  
 and project managers listened. For instance, to minimize  
 the impact of traffic, noise and dust during construction, 
  large truck traffic was limited to between 9 a.m. and  
 3 p.m., and there were minimal road closures. 
 “The Northwest Langley Wastewater Treatment Plant  
 currently provides  wastewater treatment to 30,000  
 people in Langley and is being expanded to also serve  
 the communities of Maple Ridge and Pitt Meadows – up  
 to 230,000 people,” said Cheryl Nelms, general manager  
 of project delivery, Metro Vancouver. “The project  
 will help meet the needs of the growing population,  
 strengthen the system’s resilience to seismic events and  
 the effects of climate change, reduce odours, recover  
 energy and resources from wastewater and meet updated  
 federal regulations.” 
 According to  Alexandre  Alves, project manager at  
 HFDI, the project consisted of the design, supply and  
 installation of a temporary excavation shoring system to  
 allow the installation of the future Golden Ears Pump  
 Station. Shoring consisted of a driven sheet pile system  
 braced with a combination of internal bracing, tie-rods and  
 tie-backs to a maximum excavation depth of 11 metres. A  
 total of 278 pairs of sheets were installed with lengths up  
 to 80 feet. The shoring system also acted as a water cut-off.  
 PROJECT SPOTLIGHT 
 Aerial view of sheet pile installation at Golden Ears project, August 2020 
 24 Issue 4 2021  www.pilingcanada.ca 
 
				
/www.pilingcanada.ca